Study on the Performance of Wonogiri Reservoir as Flood Control Structure

https://doi.org/10.22146/jcef.24007

Alexander Armin Nugroho(1*)

(1) Disaster Risk Reduction Office of Central Java Province, Semarang, Indonesia
(*) Corresponding Author

Abstract


The Wonogiri reservoir was built with a primary function as flood control, especially in areas prone to flooding along the Bengawan Solo River. To find out the performance of the Wonogiri reservoir in flood control of Bengawan Solo, a study was conducted on flood hydrograph characteristics of the reservoir inflow by considering the contribution inflow from all sub-watersheds in the reservoir catchment area, at the end of December 2007. Calculation analysis flood hydrograph of Wonogiri Reservoir inflow is done with the calibration of Wuryantoro and Keduang sub-watersheds. Results of the calibration were then used reference to simulate flood hydrograph inflow in each sub-watershed catchment areas. Flood routing in the reservoir was done with the assumption that the inflow of the reservoir was left to face up a height of water in the reservoir 135.3 m (the lower flood control limit) and 138.3 m (the upper flood control limit) and then the spillway gates full-opening. Results of this research indicated that the maximum discharge inflow into the reservoir on the event of Wonogiri flood at the end of December 2007 was ranged from 3,331 to 4,993 m3/s; and it was occurred on December 26, 2007 at between 04:00 - 06:00 am. The most dominant flood hydrograph contribution into the reservoir was derived from Keduang sub-watershed. The flood in the reservoir was simulated as that the spillway gates were closed until water level of reservoir reached the minimum height of 135.3 m and 138.3 m and only until then the spillway gates full-opening. The reservoir water level reached 135.47 m on December 26, 2007 at 6:00 am and outflow was generated when the gates opened to reach 550 m3/s and then increased up to 642 m3/s at 14:00 after then it gradually decreases. The water level simulation was unable to reach 138.3 m because up to December 27, 2007 at 23:00 the water level reservoir reaches only 136.44 m. The Wonogiri reservoir flood control function still can run well and able to reduce the peak flood of 85%.

Keywords


Flood hydrograph inflow; Wonogiri Reservoir; flood control.

Full Text:

PDF


References

Kodoatie, R. J. & Sjarief, R., 2006. Pengelolaan Bencana Terpadu [Integrated Management of Flood]. Jakarta: Yarsif Watampone.

Nippon Koei Co. Ltd, 1984. Manual for Operation and Maintenance, Tokyo: s.n.

Overseas Technical Cooperation Agency of Japan (OTCA), 1974. Hydrology, Sporting Record Part One, Colombo Plan expert K. Nobe (Hydrologyst), Japan: s.n.

Perum Jasa Tirta I, 2008. Banjir Bengawan Solo Desember 2007 dan Operasi Pengendalian Banjir Bendungan Wonogiri [Bengawan Solo River Flood on December 2007 and Operation of Wonogiri Reservoir as Flood Control], Surakarta: Perum Jasa Tirta I.



DOI: https://doi.org/10.22146/jcef.24007

Article Metrics

Abstract views : 1667 | views : 2127

Refbacks

  • There are currently no refbacks.




Copyright (c) 2022 The Author(s)


The content of this website is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.
ISSN 5249-5925 (online) | ISSN 2581-1037 (print)
Jl. Grafika No.2 Kampus UGM, Yogyakarta 55281
Email : jcef.ft@ugm.ac.id
Web Analytics JCEF Stats